Thursday, December 08, 2016

Glenn Saves the Day - Again

UAS Entrance Sign

UAS Construction Update for 12/09/2016

Glenn Saves the Day - Again

After discovering the two letters that were damaged during shipping,  we were looking at a 3-4 week delay to get the manufacturer to fabricate some new ones.    We decided to take the letters to Glenn Ramsey our UAS Maintenance/Welding Adjunct Professor/Handy-man and all around good guy.  Glenn performed his magic and had them back to us the next day.

 

Fixed Sign A_3
Fixed Sign A_3
 

So you may ask, why are the fixed letters still sitting on my desk?   Unfortunately the manufacturer did not ship all of the sign parts and we have had to wait for them to arrive.  The Contractor thinks they will be ready to get back on this project early next week and be complete by the end of the week.  

We have waited this long.  I guess we can wait a little more.  “Just like Christmas”

Nathan Leigh – UAS Project Manager